During Winter Storm Fern, Texas cryptocurrency miners cut their demand by an estimated 4,100 megawatts, nearly 5% of the peak consumption forecast by ERCOT. The grid operator has nevertheless identified groups of sites exposed to the same grid fault, including Riot’s mine in Corsicana, to limit their simultaneous consumption. The group threshold planned by ERCOT is roughly 2,500 megawatts, and the allocations assigned to participating sites, totaling 2,720 MW, are not triggered only when electricity is scarce. Riot recorded about $24.7 million in power credits in the third quarter, while its agreement with Anthropic could require the company’s consent before reducing power to the tenant once the first 910 MW block is scheduled to come online in June 2027.