Crusoe has signed a contract with ProEnergy for 13 aeroderivative gas turbine generator sets, adding 650 MW of on-site capacity for its upcoming hyperscale data center projects. The deal, signed on April 16, 2026, calls for delivery by summer 2027, while average delivery times for new gas turbines in the United States have reached about six years. Each 50 MW PE6000 unit offers fast-start capability and can run on several fuels. The order reflects intense worldwide competition for turbines, with global orders exceeding 100 GW against annual manufacturing capacity of 60 to 70 GW. Crusoe had also ordered nearly 1 GW of systems from GE Vernova, but canceled a $1.25 billion order for 29 Boom Supersonic turbines in September 2026.