Atlas Energy Solutions saw its stock surge up to 19% on September 25 after announcing two cost reimbursement agreements with a frontier AI lab totaling approximately $613.5 million. The deals cover balance-of-plant infrastructure and 283 MW of Caterpillar natural gas generators, plus a 328 MW commitment slated for delivery in 2027, bringing combined capacity to 611 MW. The stock traded to an intraday peak of approximately $13.13. Originally a frac sand supplier for the Permian Basin, Atlas is pivoting its model toward on-site power generation for data centers. While the cost reimbursement structure mitigates Atlas’s financial risk, any delay or cancellation of the AI lab’s data center buildout remains a vulnerability factor.