Wallonia inspectors ordered work to stop at Google’s Farciennes site, where about 300 workers were building a data center despite an amended permit revoked in August over water consumption and drought risk. Three days earlier, a Virginia judge halted another Google campus in Botetourt County after local supervisors violated public-records law by approving the project behind closed doors. The rulings illustrate contrasting approaches: in Europe, regulators directly enforce environmental permits, while in the United States, projects remain subject to local procedures and judicial challenges. Neither halt concerned infrastructure costs, with infrastructure operator Alphabet reporting $132 billion in annual revenue, but rather permit compliance and approval procedures.