Rapidus reportedly has not yet demonstrated working 2nm SRAM cells, a key test that was due to be completed in summer 2026. The company is said to be several months behind its internal schedule, threatening its target of starting mass production in the second half of fiscal year 2027. Particle-control problems in its cleanrooms could complicate large-scale manufacturing and potentially push production back into fiscal year 2028. The Japanese government has invested more than 2 trillion yen in the company, but future funding is tied to the completion of specific technical milestones. Rapidus and Japan’s minister of Economy, Trade and Industry nevertheless maintain that the schedule remains unchanged.