Bitdeer Technologies Group, a Singapore-based company listed on Nasdaq under the ticker BTDR, plans to begin its 901 capacity delivery in January 2027, targeting 67 MW by Q2 2027. The company is expanding its AI cloud and high-performance computing business, primarily in Malaysia. The A201 data center in Johor Bahru carries approximately 21.7 MW of IT capacity with over 70% already contracted, expected to generate more than $1.7 billion in revenue over five years. With the A202 site adding 65.1 MW by Q3 2027, the Johor Bahru campus will reach 86.8 MW. Bitdeer aims for 350 MW of AI Cloud capacity by Q1 2028, having already secured approximately 333.5 MW and a revenue backlog of around $2.9 billion, while maintaining its Bitcoin mining operations.